Bağıştaş 1 Dam
Bağıştaş 1 Dam | |
---|---|
Official name | Bağıştaş 1 Baraji ve HEPP |
Country | Turkey |
Location | Bağıştaş, İliç district, Erzincan Province |
Coordinates | 39°26′57.54″N 038°31′22.61″E / 39.4493167°N 38.5229472°E |
Purpose | Power |
Status | Operational |
Construction began | 2011 |
Opening date | 2015 |
Owner(s) | Ictas Enerji Uretim ve Ticaret AS |
Dam and spillways | |
Type of dam | Embankment |
Impounds | Karasu River |
Height | 50 m (160 ft) |
Reservoir | |
Catchment area | 15,587 km2 (6,018 sq mi) |
Commission date | 2015 |
Type | Conventional |
Turbines | 3 x 44.7 MW, 1 x 6.3 MW Francis-type[1] |
Installed capacity | 140.4 MW |
The Bağıştaş 1 Dam is an embankment dam on the Karasu River near Bağıştaş in İliç district of Erzincan Province, eastern Turkey. The primary purpose of the dam is hydroelectric power generation and it supports a 140.4 MW power station. Construction began in 2011 and the generators were commissioned in 2015. It was officially dedicated by President Recep Tayyip Erdogan on 14 January 2016. The dam and power plant are owned and operated by Ictas Enerji Uretim ve Ticaret AS.[2]
See also
[edit]- Bağıştaş 2 Dam – downstream
References
[edit]- ^ "Hydroelectric Plants in Northern Turkey - other regions". IndustCards. Archived from the original on 2013-01-03. Retrieved 4 March 2016.
- ^ "Prime Minister Recep Tayyip Erdogan, 99 dams and HES is speaking at the opening ceremony, erzincan Bağıştaş 1 Dam and HEPP Opening Performing, Icdas Holding İÇDAŞ Yö" (in Turkish). Haber 24. 16 January 2016. Archived from the original on 7 March 2016. Retrieved 4 March 2016.