Eppenberg Tunnel

Eppenberg Tunnel
Construction site at Wöschnau portal, August 20
Overview
Official nameGerman: Eppenbergtunnel
LineAarau–Olten line
LocationSolothurn, Switzerland
Coordinates47°22′13″N 8°00′40″E / 47.3704°N 8.0112°E / 47.3704; 8.0112
SystemSwiss Federal Railways (SBB CFF FFS)
StartWöschnau, canton of Solothurn, Switzerland
EndSchönenwerd, canton of Solothurn, Switzerland
Operation
Work begun2 May 2015
Opened12 October 2020
OwnerSBB CFF FFS
OperatorSBB CFF FFS
TrafficRailway
CharacterPassenger, Freight
Technical
Length3.114 km (1.935 mi)
No. of tracksOne double track tube
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrified15 kV 16.7 Hz
Operating speed160 km/h (99 mph)

The Eppenberg Tunnel is a railway tunnel in the Canton of Solothurn, Switzerland. It is part of the 'Future Development of Railway Infrastructure' plan (German: Zukünftige Entwicklung der Bahninfrastruktur or 'ZEB') and increases capacity on the Aarau–Olten line in the Schönenwerd–Däniken section.[1][2][3]

A particularly constraining bottleneck in the Swiss rail infrastructure is in the section between Aarau and Olten,[4][5] which has only two tracks at Eppenberg-Wöschnau, Schönenwerd and Gretzenbach. The route has to be shared by international and national passenger trains as well as freight. Hence quadrupling the complete line between Aarau and Olten had high priority among infrastructure projects.

The main purpose of the tunnel is to increase capacity. The two additional tracks in parallel with the existing double track line effectively create a four track line.

The Federal Assembly adopted the law authoring the 'ZEB' programme in the spring session of 2009, authorising the budget for the Eppenberg tunnel.[6][7] Due to the large financial requirements for the New Railway Link through the Alps project, construction of the Eppenberg tunnel only began in 2015.

Planning

[edit]

The project is planned and managed by Swiss Federal Railways (SBB) Infrastructure in Olten. The Eppenberg tunnel is the core of the approximately 3.5 km long new line, which will pass south of the center of Schönenwerd and will have a straighter alignment than the existing line, which has a tight curve in Schönenwerd. Nominal line speed in the tunnel is 160 km/h.[8] Revenue services through the tunnel will begin with the new timetable on December 13, 2020.

The western tunnel portal is located in the area of the municipality of Gretzenbach. Where the future tunnel passes under the road, it was to be built by the cut and cover method. The tunnel will be 3114m long, this length is divided into the 125m cut and cover section at the Gretzenbach portal, the 2616m tunnel section (around 600 meters with the hydroshield method) and the 373m cut and cover section at Wöschnau portal.

The eastern tunnel portal will be built to the west of the Wöschnau district. In the vicinity of the future underpass under Route 5, a deep hole was dug in which the tunnel boring machine that excavated the main part of the tunnel was assembled.

As part of the same plan, two overpasses will be built in the approach to Olten station, which will largely eliminate at-grade crossings at the Olten junction.

Construction

[edit]

In advance, the SBB built a new signal box in Wöschnau for traffic management during the construction period.

In autumn 2014, work began on the construction site near Wöschnau and Gretzenbach. This included clearing, earth moving, slope protection, demolition work, road construction and other measures. The Gretzenbach river was diverted. The substructure for the additional track began at Däniken.

On 2 May 2015, a tunnel construction party with the official groundbreaking took place at the construction site near Wöschnau, in which Federal Counsellor Doris Leuthard, the SBB Group Management, the Government Council of the Canton of Aargau and the Government of the Canton of Solothurn participated.[9]

ARGE Marti Eppenberg won the contract for the project for CHF885mio. The construction company Huber from Eppenberg-Wöschnau was a contractor.

The excavation of the tunnel was used to fill the dismantled Kölliken hazardous waste landfill.[10]

Operation

[edit]

The SBB inaugurated the tunnel on 12 October.[8] Revenue services through the tunnel begun with the new timetable on 13 December 2020. [11]

Map

[edit]
Alignment of the Eppenberg Tunnel

References

[edit]
  1. ^ "Zukünftige Entwicklung der Bahninfrastruktur (ZEB)" (in German). Federal Office of Transport. Retrieved 2024-11-04.
  2. ^ "ZEB: Zukünftige Entwicklung Bahninfrastruktur" (in German). Swiss Federal Railways. Retrieved 2024-11-04.
  3. ^ "Eppenbergtunnel bewährt sich in den ersten 100 Betriebstagen – jetzt sind alle vier Gleise offen". Solothurner Zeitung (in German). Solothurn: CH Regionalmedien AG. 2021-03-23. Retrieved 2024-11-04.
  4. ^ Baranzini, Fabio (2020-11-16). "Das Ende der SBB-Achillesferse: Nach mehr als 30 Jahren ist der Eppenbergtunnel fertig". Aargauer Zeitung (in German). Aarau: CH Regionalmedien AG. Retrieved 2024-11-05.
  5. ^ SBB Geschäftsbericht 2020 (PDF) (Report) (in German). Bern: Swiss Federal Railways. p. 19. Retrieved 2024-11-05.
  6. ^ von Arx, Christian (30 November 2009). "«Bahn frei für den Eppenbergtunnel!»". Luzerner Zeitung (in German). CH Media. Retrieved 8 November 2024.
  7. ^ "Bundesgesetz über die zukünftige Entwicklung der Bahninfrastruktur (ZEBG)" (PDF). www.fedlex.admin.ch (in German). Federal Chancellery of Switzerland. 2009-03-31. Retrieved 8 November 2024.
  8. ^ a b "Eppenberg tunnel opens for traffic". Railway Gazette International. Railway Gazette International. 14 October 2020. Retrieved 16 October 2020.
  9. ^ "15-Minuten-Takt – Startschuss für Ausbau". 20 minuten (in German). Zurich: TX Group AG. 2015-05-02. Retrieved 2024-11-04.
  10. ^ Adrian Meyer (2016). "Die Spuren der Schandtat von Kölliken sind beseitigt – Der Dreck ist weg". Blick.ch. Retrieved 2018-05-06.
  11. ^ "Erste Testfahrten durch neuen SBB-Eppenbergtunnel". Derbund.ch. 2020-09-11. Retrieved 2020-09-30.