Mundra Ultra Mega Power Plant

Mundra Ultra Mega Power Project (TATA POWER LIMITED)
Map
CountryIndia
LocationTunda village in Mundra, Kutch district, Gujarat
Coordinates22°49′20″N 69°31′56″E / 22.82222°N 69.53222°E / 22.82222; 69.53222
StatusOperational
Construction began2007
Commission date2012-2013
OwnerTata Power
OperatorCoastal Gujarat Power Ltd.
Thermal power station
Primary fuelSubbituminous coal
Power generation
Units operational5 × 800 MW
Make and modelToshiba, Doosan
Nameplate capacity4,000 MW

Mundra Ultra Mega Power Project or Mundra UMPP is a subbituminous coal-fired power plant in Tunda village at Mundra, Kutch district, Gujarat, India. It is the 3rd largest operational power plant in India. The coal for the power plant is imported primarily from Indonesia. The source of water for the power plant is sea water from Gulf of Kutch. The power plant is owned by Tata Power. The special purpose vehicle Coastal Gujarat Power Ltd (CGPL) was incorporated on 10 February 2006.[1]

Capacity

[edit]

The capacity of the project is 4,000 MW with 5 units of 800 MW each.

Stage Unit Number Installed Capacity (MW) Date of Commissioning
1st 10 800 March 2012[2]
2nd 20 800 July 2012[3]
3rd 30 800 October 2012[4]
4th 40 800 January 2013[5]
5th 50 800 March 2013[6]
Total Five 4000

Technology

[edit]

The plant uses super-critical boiler technology. Compared to other sub-critical plants in India, Mundra UMPP would use 1.7 million tonnes of less coal per year while generating the same quantum of power.[4] Boilers are supplied by Doosan and turbines are supplied by Toshiba.

Buyers

[edit]

Tata Power entered into a power purchase agreement for the sale of the 4,000 MW capacity of the plant.[7]

State Contracted Capacity (MW)
Gujarat 1,805
Maharashtra 760
Punjab 475
Rajasthan 380
Haryana 380
Non-PPA 200
Total 4000

In January 2013, the company terminated the PPA with the Rajasthan distribution companies - Jaipur Vidyut Vitaran Nigam, Jodhpur Vidyut Vitaran Nigam and Ajmer Vidyut Vitaran Nigam - due to non-compliance on payment security related issues and consistent failure on the part of the discoms as procurers to fulfill their obligations, including collateral arrangements. The company will now have to option of selling the power in the merchant market.[8]

Controversy over power tariff

[edit]

Tata Power won the project through a competitive tariff based bidding route in 2006 by quoting 55% of the fuel cost as a non-scalable component and a levelised tariff of Rs 2.26 per kWh or unit.[9] The Indonesian government's decision in 2010 to change its mining law to bring coal price exported from Indonesia in line with the international market[10] caused an increase in coal price and under-recovery of costs at Mundra UMGPP (and similarly impacted Adani Power's 4620 MW Mundra plant). The loss led to an erosion of Tata Power's net worth by over 3800 crore in 3 years.[11] The company had accordingly petitioned the Central Electricity Regulatory Commission for compensatory tariff hike, and later for compensatory relief.

In December 2016 the Central Electricity Regulatory Commission allowed compensatory relief for Tata Power from the electricity procuring states under the Force Majeure clause after having awarded in February 2014 a compensatory tariff of 52 paise per unit;[12] however the orders are subject to the outcome of a pending appeal in the Supreme Court. The compensatory relief also is to be adjusted against profits made in sale of coal from the Indonesian mines where the companies have a stake.

In 2007, Tata Power had acquired a 30% stake in two Indonesian thermal coal companies owned by PT Bumi Resources—PT Kaltim Prima Coal (KPC) and PT Arutmin Indonesia— for about $1.1 billion[13] as part of a strategy to provide low cost coal for the Mundra UMPP.

In 2014, Tata Power agreed to sell a 30% stake it held in PT Arutmin Indonesia, to the Bakrie Group for a sale consideration of $510 million (later revised to $400 million). No date has been set for his sale closure, which is pending regulatory clearances from the authorities

The company had requested Central Electricity Regulatory Commission to allow a tariff hike to about Rs 3.00 per unit[14]

The company had petitioned the CERC to rule whether the company can claim relief under any/all of the following:[15]

  • Article 13 of the PPA due to Change in Law

The company stand is that the definition of law under the PPA is an inclusive (and not exhaustive) definition. The definition of law covers 'any law' and is not restricted to Indian law. The term 'law' is required to be interpreted in a contextual basis with a view to give business efficacy to the PPA since the project is based on imported coal and the fuel supply arrangements are a part of the Project Documents. The definition of Law must be given a plenary meaning and cannot be read down by confining it to Indian laws. The promulgation and enforcement of 'Regulation of Ministry of Energy and Mineral Resources No. 17 of 2010 regard procedure for Setting Mineral and Coal Benchmark Selling Price' dated 23.09.2010 by Government of Indonesia ("Indonesian Regulations") led to an unprecedented, uncontrollable and unforeseeable rise in coal prices which constitutes a 'Change in Law' under the PPA.

  • Article 12 of the PPA, pertaining to Force Majeure

The definition of Force Majeure under Article 12.3 of the PPA covers "any event or circumstance or combination of events or circumstances that wholly or partly prevents or unavoidably delays an Affected Party in performing its obligations under the PPA to the extent such events or circumstances are not within the reasonable control, directly or indirectly of the Affected Party and could not have been avoided if the Affected Party had taken reasonable care". Tata Power is arguing that the promulgation of the Indonesian Regulation is an event which is beyond its control and has made it impossible for the company to perform its obligations as per the contracted price. So this is covered as a Force Majeure event under Article 12.3 of the PPA.

  • CERC's power to 'regulate' tariff by exercising its powers under Section 79(1)(b) of the Electricity Act, 2003.

Tata Power is arguing that CERC has the power under Section 79(1)(b) of the Electricity Act, 2003 to revisit/restructure the tariff for a power project if the project has lost its viability and it has become commercially impossible for the project owner to perform its contractual obligations.

On 18 July 2012 the Central Electricity Regulatory Commission deferred a decision on Tata Power's petition. Central Electricity Regulatory Commission has asked the company to go back and take recourse to the dispute resolution provisions of the power purchase agreement (PPA) before seeking relief from the Central Electricity Regulatory Commission.[16]

On 25 October 2012 the CERC admitted the petition for hearing since the consultative process under Article 17.3 of the Power Purchase Agreement (PPA) between Coastal Gujarat Power Ltd and the lead procurer, Gujarat Urja Vikas Nigam Limited (GUVNL) had failed. The petition will now be renotified for hearing on 4 December 2012.[17]

See also

[edit]

References

[edit]
  1. ^ "Coastal Gujarat Power Ltd (CGPL)". Tata Power. Retrieved 9 January 2012.
  2. ^ "Tata Power commissions Mundra UMPP's first 800 MW unit". Business Standard. Press Trust of India. 9 March 2012. Retrieved 9 January 2013.
  3. ^ Shankar Subramaniam. "Business Line : Companies News : Tata Power's Mundra plant Unit II becomes operational". Business Line. Retrieved 9 January 2013.
  4. ^ a b "Tata Power synchronises third 800 MW unit at Mundra UMPP - PTI". Moneycontrol.com. 8 October 2012. Retrieved 9 January 2013.
  5. ^ Vora, Rutam (7 January 2013). "Tata Power synchronises unit 4 of Mundra UMPP". Business Standard. Retrieved 9 January 2013.
  6. ^ "Tata Power commissions Mundra UMPP 5th unit". 25 March 2013.
  7. ^ "Tata Power sees Rs 3,000 crore equity erosion in Mundra UMPP project: Sources - Economic Times". The Economic Times. Press Trust of India. 7 October 2012. Archived from the original on 5 March 2016. Retrieved 9 January 2013.
  8. ^ Kumar, Abhineet (5 January 2013). "Rajasthan break to put Tata's Mundra power in open market". Business Standard. Retrieved 9 January 2013.
  9. ^ "Mundra braces for CERC order". The Financial Express. 26 September 2012. Retrieved 9 January 2013.
  10. ^ DNA India (3 July 2012). "On Mundra UMPP, great confusion, no clear solution - Money - DNA". Daily News and Analysis. Retrieved 9 January 2013.
  11. ^ "Mundra UMPP has eroded Tata Power's net worth by Rs 3,800 crore in three years: Anil Sardana". The Financial Express. 25 March 2016. Retrieved 10 December 2016.
  12. ^ Debapriya Mondal (8 December 2016). "Major relief for Tata Power, Adani in compensatory tariff case". ET EnergyWorld. Retrieved 10 December 2016.
  13. ^ Live Mint (1 December 2016). "Tata Power cuts sale consideration for Arutmin mine in Indonesia to $246 mn". Live Mint. Retrieved 10 December 2016.
  14. ^ "Tata Power seeks higher tariff for Mundra UMPP". Business Standard. Press Trust of India. 17 July 2012. Retrieved 9 January 2013.
  15. ^ Central Electricity Regulatory Commission India (4 December 2012). "Record of Proceedings in Petition No. 159 of 2012" (PDF). cercind.gov.in. Retrieved 9 January 2013.
  16. ^ "CERC defers decision on Tata Power plea". The Financial Express. 20 July 2012. Retrieved 9 January 2013.
  17. ^ http://www.cercind.gov.in/2012/orders/Signed_Order_159_2012.pdf [bare URL PDF]