Tauhara Power Station
Tauhara Power Station | |
---|---|
Country | New Zealand |
Location | Taupō, New Zealand |
Coordinates | 38°40′5″S 176°9′4″E / 38.66806°S 176.15111°E |
Status | Under construction |
Construction began | 31 March 2021[1] |
Owner | Contact Energy |
Power generation | |
Nameplate capacity | 174 MW[2] |
External links | |
Website | Tauhara webpage |
The Tauhara Power Station is a geothermal power station north of Taupō in New Zealand. Previously known as Tauhara 2, the project is being developed by Contact Energy and Tauhara Moana Trust[3] and is expected to be operational in the third quarter of 2024.
Background
[edit]Stage 1 of the wider Tauhara project is operational as the Te Huka Power Station. This is a 23 MW binary plant supplied with geothermal steam from the Tauhara field.[4]
Tauhara Stage 2
[edit]The application for resource consents for a 250 MW power station was submitted in February 2010. The Minister for the Environment determined that this project was one of national significance, and referred it to an independent Board of Inquiry.[5] The resource consents were granted in December 2010.[6] It was the first infrastructure project to be processed under the new Board of Inquiry process administered by the Environmental Protection Authority. In August 2019 Contact Energy began drilling four wells to further characterize the geothermal reservoir on the field and inform a final decision on whether to build a new power plant.[2]
The project is expected to cost around $580 million.[7]
In February 2021 Contact Energy announced that it planned to issue $400 million of new shares to raise capital to build the plant.[8]
Construction of the station began in March 2021[1] In February 2022 Contact announced that the completion date would be delayed to mid-2023, but that the output of the station would increase to 168 MW.[9] In November 2023, the target for the station to be operational was pushed to the third quarter of 2024, with an output of 152 MW, rising to 174 MW later.[10]
See also
[edit]References
[edit]- ^ a b Beck, David (31 March 2021). "Tauhara geothermal power station: Prime Minister Jacinda Ardern marks beginning of construction". Rotorua Daily Post.
- ^ a b "Our Projects". Contact Energy.
- ^ Akuhata, Whare (7 October 2011). "Maori trust signs geothermal drilling deal with Contact Energy". New Zealand Herald.
- ^ "Energy In New Zealand". MBIE. July 2014.
- ^ Smith, Nick (23 March 2010). "First EPA request referred to board of inquiry" (Press release).
- ^ "Report and decision". Environmental Protection Authority. 10 December 2010.
- ^ "Contact to build Tauhara geothermal power station; will raise $400m in equity" (Press release). Contact Energy. 15 March 2021.
- ^ "Contact Energy's Tauhara geothermal power station completion date delayed". RNZ. 8 February 2022. Retrieved 8 February 2022.
- ^ "UBS Geothermal Commissioning Update". NZX. 10 November 2023.
External links
[edit]- Contact Energy - Tauhara Power Station